Material takeoff for concrete blocks and mortar from the wall you enter. It does not replace the drawings or the project of a structural engineer: the wall type, grouting, reinforcement, lintels and footing come from the design and the building code, and the local building department decides. Counts follow NCMA TEK 4-2A for 8 x 16 in face units.

Maintained by BuildSolver · Updated

Calculator · Construction

Concrete block wall calculator

Enter the length and height of a block wall, the doors and windows in it, a breakage allowance and the mortar yield per bag, and this page gives the concrete blocks to order and the bags of mortar. A nominal 8 x 16 in block covers 128 sq in, so a square foot of wall takes 1.125 blocks. The default is a 100 sq ft wall, the area behind the 119-block figure in Table 1 of NCMA TEK 4-2A: 113 blocks laid, 119 with 5 percent waste, and 9 bags of mortar at 13 blocks per 80 lb bag. A 20 x 8 ft wall with a door and two windows takes 136 blocks against 189 with none. For the footing use the concrete calculator; for the steel, the rebar calculator.

  1. The length and height of the wall in feet, and for the doors and the windows the number, the width and the height of the rough opening in feet. Leave an opening group empty if the wall has none.
  2. A breakage allowance in percent (5 is the default, the figure NCMA TEK 4-2A includes), and how many blocks one 80 lb bag of mortar lays: 13 for QUIKRETE Mason Mix, 16 for the TEK 4-2A preblended mortar, or the figure on your own bag.
  3. The result gives the blocks to order, the blocks laid in the wall, the bags of mortar rounded up and the net wall area, with the arithmetic for each.
  4. The notes say when the wall does not land on the 8 in course or the 16 in block, when openings are a large share of the wall, and what the page does not count.

Blocks and bags of mortar for a single-wythe wall of nominal 8 x 16 in face units, less openings, from NCMA TEK 4-2A and the QUIKRETE Mason Mix yield. Material only: no grout, no steel, no footing, no design.

The length of the wall in feet, corner to corner. For a wall with returns add the legs together. The page accepts 1 to 2,000 ft.

From the top of the footing or slab to the top of the wall, in feet. Nominal 8 in courses stack to 8 ft at 12 courses. The page accepts 1 to 40 ft.

How many door openings are in the wall, a whole number. Leave the three door fields empty if there are none.

The width of the rough opening in feet. Needed with the number and the height.

The height of the rough opening in feet, up to the underside of the lintel. An opening taller than the wall is refused.

How many window openings of one size are in the wall. Leave the three window fields empty if there are none. For windows of different sizes, enter a count and an average size that give the right total area.

The width of the rough opening in feet. Needed with the number and the height.

The height of the rough opening in feet, sill to head.

Added to the block count for breakage and cuts. NCMA TEK 4-2A includes about 5 percent in its 119 units per 100 sq ft, and 5 is the default here. The page accepts 0 to 50.

Both figures are read from the sources named below the calculator and differ; 13 gives more bags. Take the yield from the label of the mortar you buy if it states one.

Example result for the default inputs

Wall 12.5 x 8 ft of nominal 8 x 8 x 16 in block, no openings, 5 percent waste, 13 blocks per 80 lb mortar bag.

Blocks to order

119 8 x 8 x 16 in

Blocks laid in the wall

113 before waste

Mortar bags

9 x 80 lb

Net wall area

100.0 sq ft

Calculation details
Wall12.5 ft x 8 ft = 100.0 sq ft
Net area100.0 sq ft, no openings
Blocks per sq ft144 sq in / 128 sq in (nominal 16 x 8 in face) = 1.125; 100.0 x 1.125 = 112.50 blocks, 113 laid
Blocks to order112.50 x (1 + 5 / 100) = 118.13, rounded up to 119
Courses and blocks per course12.00 courses of 8 in, 9.38 blocks of 16 in per course (nominal)
Mortar yieldQUIKRETE Mason Mix, 80 lb bag: 13 blocks
Mortar bags113 laid / 13 = 8.69, rounded up to 9 bags, 720 lb
  • A wall 12.5 ft long is 9.38 blocks of 16 in per course, not a whole number. The last block in each course is cut, and TEK 4-2A cautions that non-modular layouts can significantly increase the number of units.
  • The QUIKRETE sheet gives 13 blocks as 'up to' per 80 lb bag and describes a full bed of mortar about 1/2 to 3/4 in thick, where TEK 4-2A counts face shell bedding. The NCMA TEK 4-2A figure for preblended mortar is 16; choose it, or your own figure, if your supplier's sheet says so.
  • Mortar bags are counted from the blocks laid, not the blocks ordered, since broken blocks take no mortar. The mortar yield is a rule of thumb and varies with the mason, the joint and the layout. Sand, lime and water for site-mixed mortar are not counted.
  • This page counts blocks and mortar only. Cell grout, reinforcing steel, bond beams, lintels, pilasters, special shapes (corner, half and bond beam units), the footing and the structural design are not included; a structural engineer or the drawings set them.

For estimation purposes only. Consult a licensed engineer for final designs.

Get this result as a PDF, free account

Sign up with your email. Back on this page in the same browser, your inputs are filled in. No card.

Size the footing concrete

Free without signup

How the blocks and the mortar are found

The page takes the wall area less the openings, multiplies it by the number of nominal 8 x 16 in block faces in a square foot, adds a breakage allowance and rounds up, then divides the blocks laid by the number one bag of mortar lays. It does not depend on the wall thickness, and it does not count grout or reinforcement.

Net wall area
net area = length x height - openingsOpenings are the number x width x height of the door group and of the window group. A 20 x 8 ft wall is 160.0 sq ft; one 3 x 7 ft door and two 4 x 3 ft windows take 45.0 sq ft, leaving 115.0 sq ft. NCMA TEK 4-2A says to subtract the area of windows, doors and other openings from the total wall area.
Blocks per square foot
blocks = net area x 144 / 128 = net area x 1.125A nominal 8 x 16 in unit shows 128 sq in of face, which is the 8/9 sq ft in TEK 4-2A, so one sq ft takes 144 / 128 = 1.125 blocks and 100 sq ft takes 112.5 before waste. The 100.0 sq ft default is 112.5 blocks, 113 laid. The count does not change with the width of the unit: TEK 4-2A states it is independent of unit width.
Blocks to order
order = ceil(net area x 1.125 x (1 + waste / 100))112.5 x 1.05 = 118.125, rounded up to 119. That is the 119 units per 100 sq ft in Table 1 of TEK 4-2A, which includes about 5 percent for waste and breakage. With no waste the default is 113.
Mortar bags
bags = ceil(blocks laid / blocks per bag)One 80 lb bag of QUIKRETE Mason Mix lays up to 13 blocks of 8 x 8 x 16 in, so 113 / 13 = 8.69, rounded up to 9 bags, 720 lb. At the 16 per bag of TEK 4-2A for preblended mortar it is 7.06, 8 bags. Bags are counted from the blocks laid, not the blocks ordered.
Courses and blocks per course
courses = height x 12 / 8, blocks per course = length x 12 / 16A 8 ft wall is 12 courses of 8 in. A 12.5 ft wall is 9.375 blocks of 16 in per course, so the last block in each course is cut. The count by area does not see that; TEK 4-2A cautions that non-modular layouts and numerous returns and corners can significantly increase the units and the mortar.

Six block walls, 8 ft high

Each row is a wall of nominal 8 x 8 x 16 in block, 8 ft high, with 5 percent waste, worked with the same function as the form. A 12.5 x 8 ft wall (no openings) takes 119 blocks and 9 bags of mortar at 13 blocks per bag, and a 40 x 8 ft wall (no openings) takes 378 blocks and 28 bags. The last column is the bag count at the 16 blocks per bag of NCMA TEK 4-2A.

Net area, blocks laid, blocks to order and mortar bags for six block walls
WallOpeningsNet area, sq ftBlocks laidBlocks to orderBags at 13Bags at 16
12.5 x 8 ftno openings100.011311998
16 x 8 ftno openings128.0144152129
20 x 8 ft1 door 3 x 7 ft, 2 windows 4 x 3 ft115.0130136109
24 x 8 ft1 door 3 x 7 ft171.01932021513
32 x 8 ft2 doors 3 x 7 ft, 4 windows 4 x 3 ft166.01871971512
40 x 8 ftno openings320.03603782823

Bags are counted from the blocks laid. The wall thickness does not enter: NCMA TEK 4-2A counts units from the wall area regardless of unit width. The mortar yields are the QUIKRETE Mason Mix figure (up to 13 blocks per 80 lb bag) and the TEK 4-2A figure for preblended mortar (16 per 80 lb bag).

Standards and data sources

  • NCMA TEK 4-2A, Estimating Concrete Masonry Materials (2004, replaces TEK 4-2) - The source of the unit count and one of the two mortar yields. Read in the PDF: a conventional unit of nominal 8 in height and 16 in length exposes 8/9 sq ft, 119 units per 100 sq ft with about 5 percent waste (Table 1); the count is independent of unit width; openings are subtracted from the wall area; and in Table 2 one 80 lb bag of preblended mortar lays 16 conventional units, with face shell bedding assumed and the estimates independent of unit width. TEK notes are now published by the Concrete Masonry and Hardscapes Association.
  • QUIKRETE Mason Mix data sheet, Product No. 1136 (revised November 2020) - The source of the 13 blocks per bag. Read in the PDF: each 80 lb bag of Mason Mix will lay up to 37 standard bricks or 13 standard 8 x 8 x 16 in blocks; the standard formulation meets ASTM C270 and C1714 as Type S mortar. The sheet describes a full bed of mortar about 1/2 to 3/4 in thick on the base and gives no waste allowance for that yield. ASTM C270 and C1714 themselves, and the ASTM C90 unit standard, are sold by ASTM and were not read for this page.

Limitations of this calculator

  • This page counts concrete blocks and bags of mortar for a single-wythe wall you describe. It is a takeoff aid for a quote or an order, not a design. It does not replace the drawings or the design of a structural engineer, and the building department decides what a wall must be.
  • Only the conventional nominal 8 x 16 in face is supported. Half-high units (4 x 16 in) and half-length units (8 x 8 in) take twice as many per sq ft in TEK 4-2A Table 1, 238 per 100 sq ft, and brick-sized units far more; none of them is in this calculator. The unit width (4, 6, 8, 10 or 12 in) does not change the count by area, since the face is the same.
  • The count is by area, as TEK 4-2A does it. Corner units, bond beam units, pilasters, jamb and lintel units and cut blocks at a length that is not a multiple of 16 in are counted as plain stretchers, and TEK says to calculate those separately. Non-modular layouts and many returns and corners add blocks; the page warns when the wall length or height does not land on the 16 in unit or the 8 in course.
  • The mortar yield is a rule of thumb. The two figures differ (13 blocks per 80 lb bag for QUIKRETE Mason Mix, stated as 'up to', and 16 for preblended mortar in TEK 4-2A), and the real yield depends on the mason, the joint, the bedding and the waste on site. The page counts bags from the blocks laid. TEK counts face shell bedding, while the QUIKRETE sheet describes a full bed of mortar, which is one reason the two yields differ. Grouted cells and bond beams use more mortar and grout and are not counted.
  • Cell grout, reinforcing steel, bond beams, lintels, anchors, ties, flashing, sealant, sand, lime and water for site-mixed mortar, and the footing are not counted. Use the concrete calculator for the footing and the rebar calculator for steel you lay out.
  • The breakage allowance is yours; the 5 percent default is the allowance TEK 4-2A states in its Table 1. Wall dimensions are in feet and the openings are rough openings the page subtracts as rectangles; it does not look at arched or sloped tops.
  • Values outside the field ranges are not accepted: wall length 1 to 2,000 ft, height 1 to 40 ft, waste 0 to 50 percent, 1 to 100 openings of 0.5 ft or more, and 1 to 200 blocks per bag. An opening taller than the wall, doors wider than the wall side by side, or openings that leave less than 1 sq ft are refused with a sentence. These bounds are this page's own, not a code's.

Common mistakes when counting block

  1. Forgetting to subtract the openings. A 20 x 8 ft wall with no openings is 189 blocks with 5 percent waste. With one 3 x 7 ft door and two 4 x 3 ft windows the page counts 136, 53 fewer, and 10 bags of mortar against 14. Subtract every opening the wall has.
  2. Mixing up the unit size. The 1.125 blocks per sq ft is for the nominal 8 x 16 in face. Half-high units 4 x 16 in take twice as many, 238 per 100 sq ft in TEK 4-2A against 119. Check the face on the block schedule before you apply the count.
  3. Treating the bag yield as exact. QUIKRETE gives up to 13 blocks per 80 lb bag and TEK 4-2A gives 16 for preblended mortar. On the 100.0 sq ft default that is 9 bags against 8. Use the yield on the bag you buy and keep a spare bag.
  4. Thinking a thicker wall needs more blocks by area. The count by area does not depend on the wall thickness: a 6 in and a 12 in wall of the same length and height show the same 16 x 8 in face, 113 laid on the 100.0 sq ft default. What changes with thickness is the weight, the price and the grout, which this page does not count.
  5. Ignoring a length that is not a multiple of 16 in. A 12.5 ft wall is 9.375 blocks per course, so the last block of each course is cut and the offcut is often scrap. The count by area does not add for those cuts, and TEK 4-2A cautions that non-modular layouts can significantly increase the number of units, so a wall full of cuts can need more than the 5 percent allowance. Plan the layout on the 8 in and 16 in module where you can.
  6. Leaving out the waste allowance. The default wall is 113 blocks with no allowance and 119 with the 5 percent TEK 4-2A includes. The 40 x 8 ft wall is 360 blocks laid and 378 to order. Breakage and cuts are real; keep the allowance as a line the client can see.

Common questions about block walls

How many concrete blocks are in a square foot of wall?

A nominal 8 x 16 in block shows 128 sq in of face, so a square foot of wall (144 sq in) takes 144 / 128 = 1.125 blocks, and 100 sq ft takes 112.5. With about 5 percent for breakage, NCMA TEK 4-2A gives 119 units per 100 sq ft. This page gets 119 for a 100.0 sq ft wall.

How many 8 x 8 x 16 blocks do I need for a 20 x 8 ft wall?

The wall is 160.0 sq ft, which is 180 blocks laid and 189 to order with 5 percent waste. If it has one 3 x 7 ft door and two 4 x 3 ft windows, subtract 45.0 sq ft: 115.0 sq ft is 130 laid and 136 to order.

How many bags of mortar do I need for a block wall?

Divide the blocks laid by the number one bag lays. QUIKRETE Mason Mix says one 80 lb bag lays up to 13 standard 8 x 8 x 16 in blocks, and NCMA TEK 4-2A gives 16 per 80 lb bag of preblended mortar. For the 113 blocks of a 100.0 sq ft wall that is 9 bags at 13 and 8 at 16. The 16 x 8 ft wall takes 12 bags at 13 per bag.

Does the thickness of the block wall change how many blocks I need?

Not by area. NCMA TEK 4-2A states that counting units from the wall area is independent of the unit width, so 4, 6, 8, 10 and 12 in units with the same 8 x 16 in face give the same count per sq ft, and its face shell mortar estimate does not depend on width either. Thickness changes the weight, the cost and the grout, which this calculator does not count.

How do I subtract doors and windows from a block wall?

Multiply the number of openings by their width and height in feet and take the total off the wall area before multiplying by 1.125. For a 20 x 8 ft wall, one 3 x 7 ft door is 21 sq ft and two 4 x 3 ft windows are 24 sq ft, so 115.0 sq ft of wall is left. Enter the door and window groups above, each with a number, a width and a height.

How much waste should I add for concrete blocks?

The default is 5 percent, the allowance NCMA TEK 4-2A includes for waste and breakage in its 119 units per 100 sq ft. Your own figure may be higher for a wall with many cuts, returns or openings. On the 100.0 sq ft default, 5 percent moves the order from 113 to 119 blocks. The page accepts 0 to 50 percent.

Does this calculator include grout, rebar or the footing?

No. It counts blocks and bags of mortar only. Filled cells, reinforcing steel, bond beams, lintels and the footing come from the drawings and a structural engineer, and the building department decides what the wall must be. Use the concrete calculator for the footing volume and the rebar calculator for the steel you lay out.

Is a nominal 8 x 8 x 16 block really 8 x 8 x 16 in?

The size name is the nominal size, and the page counts by the nominal 16 x 8 in face as NCMA TEK 4-2A does for its 8/9 sq ft per unit. The as-manufactured dimensions are not in the two documents this page was built from, so it states none. Use the size and the layout on the block schedule of the project.

Used on the same job