Concrete calculator
Enter the size of a slab, a footing or a round column and this page gives the cubic yards to order and the number of bags. A 10 ft by 10 ft patio at 4 in is 33.33 cu ft, 1.36 cu yd with 10 percent waste, or 62 bags of 80 lb. A cubic yard is 27 cu ft, which is 45 bags of 80 lb, 60 of 60 lb or 90 of 40 lb at the QUIKRETE yields. For the heat a garage on the slab needs, use the garage heater size calculator; for radiant tubing cast in it, the hydronic pipe size calculator.
- Choose a slab, a continuous footing or a round column or post hole. A job with several pieces is worked one piece at a time.
- Lengths and heights in feet. Slab thickness, footing width and depth and column diameter in inches. Set the waste allowance, 5 to 10 percent is usual, and the bag size.
- The result gives cubic yards with waste, the number of bags of the size you chose rounded up, and the bag count for the other two sizes.
Example result for the default inputs
Slab, 10 % waste, 80 lb bags.
Concrete to order
1.36 cu yd
80 lb bags
62 bags
| Volume | L x W x T / 12 = 10 ft x 10 ft x 4 in / 12 = 33.33 cu ft |
|---|---|
| Cubic yards, net | 33.33 cu ft / 27 = 1.23 cu yd |
| With 10 % waste | 33.33 cu ft x 1.1 = 36.67 cu ft = 1.36 cu yd |
| Bags of 80 lb | 36.67 cu ft / 0.6 cu ft per bag = 61.11, rounded up to 62 |
| Same order in other bag sizes | 40 lb: 123 bags, 60 lb: 82 bags, 80 lb: 62 bags |
| Yield used | QUIKRETE Concrete Mix data sheet: 40 lb 0.30 cu ft, 60 lb 0.45 cu ft, 80 lb 0.60 cu ft per bag. Another brand prints its own yield on the bag. |
For estimation purposes only. Consult a licensed engineer for final designs.
Sign up with your email. Back on this page in the same browser, your inputs are filled in. No card.
Free without signup
How the volume and the bags are found
Concrete is bought by volume. The page finds the volume of the shape in cubic feet, adds the waste allowance, converts to cubic yards (27 cubic feet each) and divides by what one bag yields, rounding up to a whole bag. Every length is changed to feet before the arithmetic, and the thickness of a slab, in inches, is divided by 12.
- Slab volume
V = L x W x T / 12Length and width in feet, thickness in inches. A 10 ft by 10 ft slab at 4 in is 33.33 cu ft, or 1.23 cu yd.- Footing volume
V = L x (W / 12) x (D / 12)Total run in feet, width and depth in inches. 60 ft at 12 in by 8 in is 40.00 cu ft, or 1.48 cu yd.- Round column volume
V = n x pi x (d / 24)^2 x HDiameter in inches, so the radius in feet is d / 24. Four piers at 12 in by 8 ft are 25.13 cu ft, or 0.93 cu yd.- Cubic yards
cu yd = cu ft / 273 ft x 3 ft x 3 ft is 27 cu ft. A 9 ft by 9 ft slab at 4 in is exactly 1.00 cu yd.- With waste
V x (1 + waste / 100)The 10 ft by 10 ft patio at 10 percent waste is 33.33 x 1.1 = 36.67 cu ft, or 1.36 cu yd.- Bags
bags = ceil(V with waste / yield)QUIKRETE prints 0.3, 0.45 and 0.6 cu ft for the 40, 60 and 80 lb bags. The patio with waste is 36.67 / 0.6 = 61.11, so 62 bags of 80 lb.
Seven pours through the same formulas
Each row is a pour worked with the same function as the form, with 10 percent waste except the last. The last row is a 9 ft by 9 ft slab at 4 in with no waste: exactly 1.00 cu yd, which is 45 bags of 80 lb. The three bag columns are the same order in each size.
| Pour | Size | Net, cu ft | Order, cu yd | 40 lb bags | 60 lb bags | 80 lb bags |
|---|---|---|---|---|---|---|
| Patio | 10 x 10 ft, 4 in, 10 % waste | 33.33 | 1.36 | 123 | 82 | 62 |
| Garage floor | 20 x 20 ft, 6 in, 10 % waste | 200 | 8.15 | 734 | 489 | 367 |
| Walkway | 3 x 20 ft, 4 in, 10 % waste | 20.00 | 0.81 | 74 | 49 | 37 |
| Strip footing | 60 ft run, 12 in wide, 8 in deep, 10 % waste | 40.00 | 1.63 | 147 | 98 | 74 |
| Eight post holes | 10 in diameter, 2 ft deep, 10 % waste | 8.73 | 0.36 | 32 | 22 | 16 |
| Four round piers | 12 in diameter, 8 ft, 10 % waste | 25.13 | 1.02 | 93 | 62 | 47 |
| One cubic yard | 9 x 9 ft, 4 in, no waste | 27.00 | 1.00 | 90 | 60 | 45 |
Volume goes with the thickness and with the square of a diameter. A slab twice as thick takes twice the concrete, and a hole twice as wide takes four times as much, which is why the size of the hole, not the post, sets the bags for post holes.
Standards and data sources
- QUIKRETE Concrete Mix, Product No. 1101-40, -50, -60, -80, -90, product data sheet (revised October 2022), Yield - The yield per bag used on this page: a 40 lb bag about 0.30 cu ft, a 60 lb bag about 0.45 cu ft and an 80 lb bag about 0.60 cu ft. The sheet also lists a typical unit weight of about 140 lb per cu ft and a 28-day compressive strength of 4,000 psi.
- NIST Special Publication 811, Guide for the Use of the International System of Units, Appendix B.8 (conversion factors for volume) - The cubic foot and the cubic yard, both defined through the cubic meter, so that a cubic yard is 3 ft x 3 ft x 3 ft = 27 cu ft. The shapes themselves are plain geometry: length x width x thickness, and pi x radius squared x height.
Limitations of this calculator
- This page works out the volume of concrete and the number of bags. It does not design the concrete. Thickness, footing width and depth, reinforcement, subgrade preparation, control joints and mix strength come from the drawings, the local building code and an engineer where the work is structural.
- The yield is the QUIKRETE figure for its Concrete Mix, rounded as the data sheet rounds it. Another brand, a high-strength or fast-setting mix, or a bag with a different weight can yield a few percent more or less. The label on the bag you buy decides.
- The result is the volume of a perfect shape. A subgrade that is not flat, a trench that is cut wider than its forms, forms that bow and concrete that stays in the barrow all take more than the geometry says. The waste allowance covers that, and 5 to 10 percent is the usual range; a rough excavation can take more.
- A slab, a footing and a set of piers poured together are three shapes. Run the page for each and add the cubic yards. The page does not handle sloped, tapered, stepped or irregular pieces; split them into rectangles and cylinders.
- Thickness, footing width and footing depth and column diameter are in inches. Lengths and heights are in feet. A thickness typed in feet is refused, because 0.33 is under the 1 inch minimum the page accepts.
- Bags are the practical way to buy small pours. A truckload of ready-mixed concrete is sold by the cubic yard, often with a minimum load or a short-load fee, and costs less per cubic yard than bags. The page gives both numbers and does not price either.
- Volume is not weight. Concrete weighs about 140 lb per cu ft, so a cubic yard is roughly 3,800 lb. Plan the barrow, the mixer and the people for that weight.
- Values outside the field ranges are not accepted: length 0.5 to 500 ft, slab thickness 1 to 24 in, footing width and depth 4 to 72 in, column diameter 4 to 72 in, height 0.5 to 40 ft, 1 to 500 columns and a waste allowance of 0 to 25 percent.
Common mistakes when figuring concrete
- Typing the thickness in feet. A 4 inch slab is 4 in the thickness field, not 0.33. The 10 ft by 10 ft patio at 4 in is 33.33 cu ft; at 6 in it is 50.00 cu ft, half as much again, because the volume goes with the thickness.
- Forgetting the waste. The patio needs 1.23 cu yd net and 1.36 cu yd with 10 percent waste: 56 bags of 80 lb against 62. Running out in the middle of a pour leaves a cold joint, which is a worse problem than a spare bag.
- Using the post size for the hole. Eight holes of 10 in diameter and 2 ft deep take 9.60 cu ft with waste, 16 bags of 80 lb. Entering a 20 in diameter, a hole twice as wide, gives 64 bags, four times as much, because the volume goes with the square of the diameter. Use the hole, not the post.
- Rounding the bags down. The 20 ft by 20 ft garage floor at 6 in is 200 cu ft, 220 cu ft with waste. At 0.60 cu ft per bag that is 366.67 bags, and the page orders 367. A fraction of a bag is a bag.
- Counting bags for a very large pour. The garage floor is 367 bags of 80 lb, about 14.7 tons of bagged mix to open, mix and place before the first batch sets. Past 2 or 3 cubic yards, ready-mixed concrete delivered by truck is the usual choice, and the volume on this page is what the supplier asks for.
- Mixing the bag sizes without checking the yield. One 80 lb bag is 0.6 cu ft and two 40 lb bags are 0.6 cu ft, the same. The walkway needs 37 bags of 80 lb, 49 of 60 lb or 74 of 40 lb. If a bag is a different brand, take its yield from the label.
Common questions about concrete volume and bags
How many cubic yards of concrete do I need for a slab?
Multiply length in feet by width in feet by thickness in inches, divide by 12 for cubic feet, then divide by 27 for cubic yards. A 10 ft by 10 ft patio at 4 in is 33.33 cu ft, or 1.23 cu yd, and 1.36 cu yd with 10 percent waste.
How many 80 lb bags of concrete are in a cubic yard?
45 bags of 80 lb, 60 of 60 lb or 90 of 40 lb, using the QUIKRETE yields of 0.6, 0.45 and 0.3 cu ft per bag. A cubic yard is 27 cu ft.
How many bags do I need for a 10 by 10 patio?
62 bags of 80 lb for a 4 in slab with 10 percent waste (82 of 60 lb, 123 of 40 lb). The net volume is 33.33 cu ft, 36.67 cu ft with waste.
How do I figure concrete for post holes or round piers?
Volume = pi x (diameter / 24)^2 x depth in feet, with the diameter in inches, times the number of holes. Eight holes of 10 in by 2 ft are 8.73 cu ft, and 16 bags of 80 lb with 10 percent waste. Four 12 in piers 8 ft deep are 25.13 cu ft.
How much waste should I add to a concrete order?
5 to 10 percent is the usual allowance. Use 5 on a flat, well-formed pour and 10 where the subgrade is rough, the trench was dug by hand or the forms are not tight. The page accepts 0 to 25 percent.
Should I buy bags or have concrete delivered?
Bags suit small jobs, post holes and repairs. The 20 ft by 20 ft garage floor is 8.15 cu yd, or 367 bags of 80 lb, which is a job for a truck. Ask the supplier about the minimum load and any short-load charge, and give them the cubic yards from this page.
How thick should a concrete slab be?
The thickness comes from the drawings and the local code, not from this page. A walk or patio slab is commonly 4 in; a garage floor or a driveway is usually thicker. The page takes whatever thickness you enter, from 1 to 24 in, and gives the volume.
How do I convert cubic feet of concrete to cubic yards?
Divide by 27, because a cubic yard is 3 ft by 3 ft by 3 ft. The walkway is 20.00 cu ft, 0.74 cu yd, and a 9 ft by 9 ft slab at 4 in is 27.00 cu ft, exactly 1.00 cu yd.