For estimation and planning use. The table cells are read from a Department of Energy reprint of the 2021 model code table, with the zone 3 wall cell as the ICC errata print it, and not from the ICC code text, and the edition and amendments of your jurisdiction govern. The page is not a compliance report. A compliance tool such as REScheck, the adopted code and a licensed designer decide the assembly. Not a substitute for a Manual J or a permit submittal.

Maintained by BuildSolver · Updated

Calculator · Building envelope

Insulation R-value calculator

The R-value of a wall is the sum of its layers, and wood framing makes a second path that lets more heat through. This page adds the layers of a wall, ceiling, floor or basement wall into a total R, takes the reciprocal for the U-factor, and multiplies by the area and the temperature difference for the heat loss. A 2x6 wall with an R-19 batt and 25.4 percent framing comes to R-15.5, a U-factor of 0.0645 and 4,514 BTU/h over 1,000 sq ft at 70 degrees F. The page then compares the cavity and continuous insulation you typed with the 2021 IECC R-value table for the climate zone, and that comparison does not use the total R. The BTU per square foot calculator gives a rule-of-thumb load for a whole house, while this page tests one assembly. For a space below grade, see the basement BTU calculator.

  1. Choose a wall, ceiling, floor or basement wall and the IECC climate zone. The page opens on a 2x6 wood frame wall with an R-19 batt in Zone 5.
  2. Give the cavity insulation, any continuous insulation, the framing depth and share, the interior finish, the sheathing and other solid layers, the air space and the air films. 25.4 percent framing is the wall figure of the Building America example.
  3. The page adds the layers of each path, weights the two paths by area, and reports R-15.5, a U-factor of 0.0645 and 4,514 BTU/h for the default wall. It then compares the cavity R and the continuous R with the table cell for the zone.

Wood frame walls, ceilings, floors and basement walls in climate zones 1 to 8, with a wood framing path of up to 40 percent. Mass walls, slabs, crawl space walls and windows are not covered. The form opens on a 2x6 wall with an R-19 batt in Zone 5.

The air film on each face and the table row both follow the assembly. A basement wall takes an inside film only.

Marine 4 uses the Zone 5 row of the table. Find the zone of a county in the code or in the map of the Department of Energy.

The R of the batt, blown or sprayed insulation between the framing as installed, such as 19 for an R-19 batt in a 2x6 wall. 0 for an empty cavity.

Foam board or similar over the studs or inside them, with no framing through it. 0 if there is none. The table counts this separately from the cavity.

3.5 for a 2x4 and 5.5 for a 2x6. The framing path takes R-1.25 per inch. Not used when the framing share is 0.

The Building America worked wall uses 25.4 percent. For joists there is no sourced figure here, so enter your own, and put insulation laid over the joists in the continuous field. 0 calculates one path through the insulation only.

Gypsum board on the room side of the assembly.

Added to both paths. 1/2 in. sheathing is 0.63 in the Building America example, a 3/4 in. wood subfloor is 0.94 and stucco is 0.08 in the state energy code table.

A closed space inside the assembly. A space open to outside air gets no credit, so pick None for a ventilated gap behind siding.

The film of still air on each surface: 0.68 inside and 0.17 outside for a wall, 0.61 inside for a ceiling and 0.92 for a floor.

The area of this assembly with the same layers, such as the net wall area without windows and doors.

Inside design temperature minus the outside design temperature, such as 70 for 70 F inside and 0 F outside.

Example result for the default inputs

Zone 5 and Marine 4, wood frame wall, R-19 cavity and R-0 continuous: total R-15.5.

Total R

15.5 hr sq ft F/BTU

U-factor

0.0645 BTU/h sq ft F

Heat loss

4,514 BTU/h

IECC table value

Not reached Zone 5 and Marine 4

Calculation details
Path through the insulationR-20.93 over 74.6 percent of the area
Path through the framingR-8.81 over 25.4 percent of the area, framing R-6.88 (5.5 in. at R-1.25 per inch)
Total R of the assemblyR-15.5, which is 1 divided by the U-factor
U-factor0.0645 BTU/h per sq ft per F, the area-weighted sum of 1/R of the paths
UA64.49 BTU/h per F over 1,000 sq ft
Heat loss4,514 BTU/h, U x 1,000 sq ft x 70 F
Insulation the table countsCavity R-19 and continuous R-0
Table R402.1.3 valueZone 5 and Marine 4, wood frame wall: 30 or 20+5ci or 13+10ci or 0+20ci
ComparisonR-19 cavity and R-0 continuous does not reach any option in the table for a wood frame wall in Zone 5 and Marine 4. With the cavity R you typed, R-10 more continuous insulation reaches R-13 cavity plus R-10 continuous.
  • The table compares the insulation you install, the cavity R and the continuous R, with its minimums. Framing, sheathing, drywall and air films do not count there, so the total R of the assembly and the table comparison are two separate results.
  • Framing at 25.4 percent of the area brings the whole assembly to R-15.5, which is 25.9 percent below the R-20.9 of the path through the insulation. The nominal R of the insulation alone overstates what the assembly delivers.
  • Where insulation fills a cavity thinner than its label thickness, the table asks for the installed R-value to be at least the table value. Type the installed R of compressed batts and not the label R.
  • A lone number in a table cell, such as 13 or 30, is read on this page as cavity insulation of that R, from the note that the first value of a pair is cavity insulation.
  • This is a preliminary check against a DOE reprint of the 2021 model code table. A permit submittal follows the code edition and amendments the jurisdiction has adopted, and a compliance tool or a designer decides the assembly.

For estimation purposes only. Consult a licensed engineer for final designs.

Get this result as a PDF, free account

Sign up with your email. Back on this page in the same browser, your inputs are filled in. No card.

How the R-value, the loss and the table check are worked out

This page does two separate jobs. It adds the layers of a wall, ceiling or floor into a total R-value, with the wood framing as a second path in parallel, and turns that into a U-factor and a heat loss in BTU/h. The page also compares the insulation you typed, the cavity R and the continuous R, with the minimums of the 2021 IECC R-value table for the climate zone. That table counts installed insulation only, so the total R of the assembly never enters the comparison. The table cells come from a Department of Energy reprint, with the zone 3 wall cell as the ICC errata print it, and not from the ICC code text, and the page says so.

Layers in series
R of a path = inside film + interior finish + air space + cavity insulation or framing + continuous insulation + sheathing and other layers + outside filmResistances of layers in the same path add. The Building America worked wall adds an inside film of 0.68, half-inch drywall at 0.45, an R-19 batt, 0.63 of sheathing and a film of 0.68 to R-21.44 through the insulation. This page uses 0.17 for the outside film of a wall, from a state energy code table.
Framing path
framing R = 1.25 x framing depth (in.)The Building America example gives 5.5 inches of framing as R-6.88, which is R-1.25 per inch. This page opens on a 2x6 wall with 25.4 percent of the area in framing, the share that example cites for walls. No sourced share for joists is used here, so it is a typed number for ceilings and floors.
Parallel path
U = (1 - f) / R(path through insulation) + f / R(path through framing), R of the assembly = 1 / UHeat is taken to flow through the insulated area and the framed area independently. The worked wall with paths of R-21.44 and R-9.32 and 25.4 percent framing comes to R-16.1 as a whole on this arithmetic. That tool is for wood framing and says not to use it for metal framing.
Heat loss
heat loss (BTU/h) = U x area (sq ft) x temperature difference (F)UA, the U-factor times the area, is the heat lost per degree. The default wall of 1,000 sq ft at a 70 degree difference loses 4,514 BTU/h at a U-factor of 0.0645, which is a UA of 64.5 BTU/h per degree.
Table comparison
reached when the cavity R is at or above the first number and the continuous R is at or above the second number of any option in the cellIn the table 13+5ci is R-13 cavity plus R-5 continuous. A Zone 5 wood frame wall reads 30 or 20+5ci or 13+10ci or 0+20ci. R-19 in the cavity with no foam reaches none of those, and R-10 of foam added reaches 13+10ci. Ceilings and floors list one number that cavity R plus continuous R must reach.

Worked examples

The default case is a 2x6 wood frame wall with an R-19 batt, half-inch drywall, 0.63 of sheathing, the standard air films and 25.4 percent framing. The path through the insulation is R-20.9 and the path through the framing is R-8.8, so the whole wall is R-15.5, which is 25.9 percent below the insulated path. Over 1,000 sq ft at 70 degrees F the loss is 4,514 BTU/h. The table for Zone 5 reads 30 or 20+5ci or 13+10ci or 0+20ci, and R-19 in the cavity with no foam reaches none of those.

The table cells used by this page, by climate zone. Ceilings and floors list one number of installed insulation, and walls and basement walls list options of cavity and continuous (ci) insulation.

Insulation minimums of the 2021 IECC R-value table by climate zone
ZoneCeiling RWood frame wallFloor RBasement wall
Zone 13013 or 0+10ci13Not required
Zone 24913 or 0+10ci13Not required
Zone 34920 or 13+5ci or 0+15ci195ci or 13
Zone 4 except Marine6030 or 20+5ci or 13+10ci or 0+20ci1910ci or 13
Zone 5 and Marine 46030 or 20+5ci or 13+10ci or 0+20ci3015ci or 19 or 13+5ci
Zone 66030 or 20+5ci or 13+10ci or 0+20ci3015ci or 19 or 13+5ci
Zone 76030 or 20+5ci or 13+10ci or 0+20ci3815ci or 19 or 13+5ci
Zone 86030 or 20+5ci or 13+10ci or 0+20ci3815ci or 19 or 13+5ci

Eight cases below run through the same functions the form uses. Foam changes the table result and also the total R. R-20 in the cavity with R-5 of foam reaches 20+5ci in Zone 5 and comes to R-21.7, and in Zone 3 the R-19 wall needs R-5 of foam to reach 13+5ci. The attic at R-38 is R-22 short of the ceiling value.

Total R, heat loss and table result for eight example assemblies
CaseSetupResult
2x6 wall, R-19 batt, Zone 5Zone 5 and Marine 4, wood frame wall, cavity R-19, continuous R-0, framing 25.4% at 5.5 in., 1,000 sq ft at 70 FR-15.5, U 0.0645, 4,514 BTU/h, table value not reached
2x6 wall, R-20 batt plus R-5 foam, Zone 5Zone 5 and Marine 4, wood frame wall, cavity R-20, continuous R-5, framing 25.4% at 5.5 in., 1,000 sq ft at 70 FR-21.7, U 0.0461, 3,227 BTU/h, table value reached
2x4 wall, R-13 batt plus R-10 foam, Zone 5Zone 5 and Marine 4, wood frame wall, cavity R-13, continuous R-10, framing 25.4% at 3.5 in., 1,000 sq ft at 70 FR-22.0, U 0.0455, 3,185 BTU/h, table value reached
2x6 wall, R-19 batt, Zone 3Zone 3, wood frame wall, cavity R-19, continuous R-0, framing 25.4% at 5.5 in., 1,000 sq ft at 70 FR-15.5, U 0.0645, 4,514 BTU/h, table value not reached
2x6 wall, R-19 batt plus R-5 foam, Zone 3Zone 3, wood frame wall, cavity R-19, continuous R-5, framing 25.4% at 5.5 in., 1,000 sq ft at 70 FR-21.2, U 0.0472, 3,302 BTU/h, table value reached
Floor over a crawl space, R-30 batt, Zone 5Zone 5 and Marine 4, floor, cavity R-30, continuous R-0, framing 10% at 9.25 in., 1,000 sq ft at 70 FR-28.2, U 0.0355, 2,482 BTU/h, table value reached
Attic floor, R-38 blown, Zone 5, no framing shareZone 5 and Marine 4, ceiling, cavity R-38, continuous R-0, no framing share, 1,000 sq ft at 70 FR-39.2, U 0.0255, 1,784 BTU/h, table value not reached
Basement wall, R-13 batt plus R-5 foam, Zone 5Zone 5 and Marine 4, basement wall, cavity R-13, continuous R-5, framing 25.4% at 3.5 in., 1,000 sq ft at 70 FR-15.8, U 0.0632, 4,422 BTU/h, table value reached

Data sources and references

Limitations of this calculator

  • The table cells are read from the Building America Solution Center reprint of the 2021 IECC table and not from the ICC code text. A jurisdiction adopts a particular edition with its own amendments, and many are on other editions, so read the table the permit office enforces. In the reprint the zone 3 wall cell reads 20 or 13+5ci or 0+15 with no ci after the 15. The ICC errata to the 2021 IECC print that cell as 0&15ci, so this page prints 0+15ci and reads that number as continuous insulation.
  • Only wood frame walls, ceilings, floors and basement walls are compared. Mass walls, slabs, crawl space walls, windows, doors and skylights are not on this page, and neither are the U-factor and total UA compliance paths of the code.
  • A lone number in a wall or basement cell, such as 13 or 30, is read as cavity insulation of that R, from the note that the first value of a pair is cavity insulation. Ceiling and floor cells are one number compared with the cavity R plus the continuous R.
  • The table compares installed insulation. Framing, sheathing, drywall and air films do not count toward it, and the page does not use the total R of the assembly for the comparison.
  • The parallel-path method is for wood framing. Metal framing, headers, corners, plates and other thermal bridges are not modeled beyond the framing share you type, and the 25.4 percent default is the wall figure of one source, not a figure for joists.
  • Film, board and air space values are defaults from one state energy code table. The air space is credited at 0.91 only when it is unventilated, a basement wall takes no outside film, and soil is not credited. Sheathing, siding and subfloor R is typed.
  • The cavity R is the installed value you type. Compression, gaps, voids, wind washing and air movement inside the assembly are not modeled, and the page does not check the R against the depth of the cavity.
  • Footnotes and special provisions of the code text, such as those for particular attic or framing conditions, are not applied. The comparison covers the main cell of each table row.
  • Heat loss is conduction through one assembly at one temperature difference. Air leakage, ground contact, solar gain and the other assemblies of the house are left out, so the figure is not a Manual J load.
  • This is a preliminary check and not a permit submittal. A compliance tool such as REScheck, the adopted code and a licensed designer decide the assembly.

Common R-value mistakes

  1. Putting the total R in the table comparison. The table lists installed insulation, so the total R of the assembly does not belong in the comparison. A default wall comes to R-15.5 in total, and the table is read with the R-19 in the cavity and the R-0 of continuous insulation. Zone 5 asks for 30 or 20+5ci or 13+10ci or 0+20ci.
  2. Reading the batt label as the wall. An R-19 batt in a 2x6 wall is sold as R-19. With 25.4 percent framing, the films, the sheathing and the drywall, the assembly comes to R-15.5, and the path through the insulation alone is R-20.9. The framing path is only R-8.8, so the whole is 25.9 percent below the insulated path.
  3. Leaving the framing out of the heat loss. Setting the framing share to 0 gives R-20.9 and 3,344 BTU/h for the default wall, against R-15.5 and 4,514 BTU/h with 25.4 percent framing. The studs carry heat the batt does not, and the difference is 25.9 percent of the insulated path.
  4. Treating R-19 as R-20 in Zone 3. The Zone 3 wall cell reads 20 or 13+5ci or 0+15ci. R-19 in the cavity falls short of the R-20, and it reaches no other option on its own. Adding R-5 of continuous foam reaches 13+5ci, and the wall then comes to R-21.2 in total.
  5. Stopping an attic at R-38 in Zone 5. A Zone 5 ceiling is listed at R-60. R-38 of blown insulation gives R-39.2 for the whole assembly, but the table is read on the R-38 alone, which is R-22 short. The films and drywall do not make up the gap.
  6. Mixing up the basement wall pairs. The Zone 5 basement wall cell reads 15ci or 19 or 13+5ci. R-13 batts alone reach none of the three, and R-5 more continuous insulation reaches 13+5ci. In Zone 3 the cell reads 5ci or 13, and R-5 of foam alone reaches it.

Common questions about R-value and the IECC table

How do I calculate the R-value of a wall?

Add the R-values of the layers in each path and weight the paths by area. A 2x6 wall with an R-19 batt has R-20.9 through the insulation and R-8.8 through the framing, and with 25.4 percent framing the whole wall is R-15.5. Wood framing lowers the result.

What is the difference between R-value and U-factor?

They are reciprocals. U is 1 divided by R, so R-15.5 is a U-factor of 0.0645 BTU/h per square foot per degree F. A higher R means less heat flow, and a lower U means the same. Either one describes the same assembly.

How do I get heat loss from an R-value?

Divide 1 by the total R for the U-factor, then multiply by the area and the temperature difference. The default wall of 1,000 sq ft at 70 degrees F loses 4,514 BTU/h. It is conduction only. Air leakage and the rest of the house add to it.

What does 13+5ci mean in the IECC table?

The first number is cavity insulation and the second is continuous insulation, so 13+5ci is R-13 in the cavity plus R-5 of continuous insulation. A cell with several options is satisfied by any one of them. The Zone 5 wood frame wall reads 30 or 20+5ci or 13+10ci or 0+20ci.

What R-value does the 2021 IECC list for a wall in Zone 5?

The reprint of Table R402.1.3 by the Building America Solution Center lists 30 or 20+5ci or 13+10ci or 0+20ci for a wood frame wall in Zone 5, R-60 for the ceiling and R-30 for a floor. Those are minimums of installed insulation. The jurisdiction adopts its own edition and amendments.

Does the framing count against the R-value in the table?

No. The table asks for the cavity insulation and the continuous insulation, and the framing is not a credit. Total R of the assembly, 15.5 for the default wall, is a separate figure that is used for heat loss and not for the table comparison.

Why is the R-value of my wall lower than the batt in it?

The studs, plates and headers form a second path with far less resistance, and heat takes the easy way through. At 25.4 percent framing the default wall is 25.9 percent below its insulated path. Films and drywall add a little back.

How is this different from the BTU per square foot calculator?

The BTU per square foot page gives a rule-of-thumb load from floor area and climate. This page works out the heat loss of one wall, ceiling or floor from its own layers and checks the insulation against the code table. Use it to test an assembly, not to size equipment.

Is there a limit on how many times I can run this?

No. This calculator runs in your browser with no daily limit and no signup. Run it for each assembly of the house and for each option you want to compare.

Used on the same job

Find the loss, then size the equipment

The heat loss of each assembly adds up to the envelope load of the house. Run the walls, the ceiling and the floor here, and then take the total to a sizing page such as the heat pump sizing calculator. For a quick room-by-room figure, see the room addition BTU calculator. You can also ask the assistant to go over an assembly with you.

Open the chat